Vista previa del material en texto
PROGRAMA POR PARTIDAS No. PARTIDA IMPORTE FECHA INI. FECHA TER. 1 PRELIMINARES 12,857.35 19-Oct 28-Oct 2 CIMENTACIÓN 118,569.87 26-Oct 8-Nov 3 MUROS, CADENAS Y CASTILLOS 140,785.25 4-Nov 17-Nov 4 CUBIERTA 95,875.14 16-Nov 20-Nov 5 ACABADOS 129,458.23 22-Nov 2-Dec 6 CANCELERÍA 75,894.65 30-Nov 6-Dec 7 INSTALACIÓN ELÉCTRICA 75,321.82 9-Nov 06/12/202 8 INSTALACIÓN HIDRÁULICA Y MUEBLES 50,483.78 11-Nov 6-Dec 9 INSTALACIÓN SANITARIA 28,546.25 11-Nov 9-Dec 10 LIMPIEZAS 2,589.36 10-Dec 11-Dec TOTAL 730,381.70 SUMA ACUM. SUMA % ACUM. % 49404.11 69,165.76 2a. Oct. 1a.Nov. 2.a Nov. 1a. Dic. 12,857.35 95,875.14 2,589.36 117321.04 23464.21 103566.58 25891.65 12649.11 63245.54 18830.46 40799.32 15692.05 9178.87 29831.32 11473.59 4567.4 14844.05 9134.8 321029.73 128026.9962,261.46 62,261.46 219063.53 281,324.99 IMPORTES