Milestones and budget Milestones Target date Actual date Impact Content development 2/2/2023 10/03/2023 The project's content requirements are entirely met, accelerating project development. Web progress 2/2/2023 10/03/2023 There will be delays in the project. Logo design 2/2/2023 10/03/2023 The firm is presently reviewing the logo draft, which resulted in the logo makeover. Budget Indicate total project funding, planned expenditure and actual expenditure. Total Project funding $26500 Planned Expenditure for this reporting period $5000 Actual Expenditure for this reporting period. $8000 Remaining budget for life of project $17000 Comments Include additional comments as required regarding overspend or surplus/underspend in this reporting period. The project budget is $5,000, but the real costs surpass $8,000. The leftover money will be designated as a contingency budget in case more cash is required.